地铁安全文明施工费费率标准动态测算研究

陈伟1 教授, 杨主张1, 容思思2, 付红阳3   

  1. 1 武汉理工大学 土木工程与建筑学院,湖北 武汉 430070
    2 武汉城市发展投资有限公司, 湖北 武汉 430019
    3 武汉工程建设标准定额管理站,湖北 武汉 430015
  • 收稿日期:2017-12-11 修回日期:2018-02-28 出版日期:2018-04-28 发布日期:2020-09-28
  • 作者简介:陈伟(1970—),男,湖北武汉人,博士,教授,博士生导师,主要从事工程项目管理方面的研究。E-mail:iamhappychen@163.com。

Dynamic calculation method of safety-civilized measure cost rate of subway project

CHEN Wei1, YANG Zhuzhang1, RONG Sisi2, FU Hongyang3   

  1. 1 School of Civil Engineering and Architecture,Wuhan University of Technology,Wuhan Hubei 430070,China
    2 Wuhan Urban Development Investment Co., Ltd.,Wuhan Hubei 430019,China
    3 Wuhan Construction Standard Management Station, Wuhan Hubei 430015,China
  • Received:2017-12-11 Revised:2018-02-28 Online:2018-04-28 Published:2020-09-28

摘要: 为有效解决目前地铁工程中安全文明施工费费率标准指导效用滞后问题,在数据时效性约束下研究该费率的实时测算。在界定地铁工程安全文明施工费内涵的基础上,将其按固定费用和变动费用精细化分析,进而统计并预测其费用投入以作为费率测算分子;构建用粒子群算法优化的最小二乘支持向量机(PSO-LS-SVM)模型,用其预测竣工结算造价,从中提取计费基数作为费率测算分母;最终形成地铁工程安全文明施工费费率标准的动态测算方法;选取武汉地区在建样本项目进行实证分析。结果表明:用动态测算方法测算的费率,能够反映实时环境下的地铁工程对安全文明施工费的需求。

关键词: 地铁工程项目, 安全文明施工费费率, 结算造价, 动态测算, 粒子群算法优化的最小二乘支持向量机(PSO-LS-SVM)模型

Abstract: For the sake of solving the problem that the standard of safety-civilized measure cost rate couldn't work effectively in time for subway project, the rate was studied based on the constraint of time. It was proposed that the subway project safety-civilized measure cost should be analyzed from the two parts of the fixed cost and variable cost according to its definition. On the basis of the analysis, the safety-civilized measure cost was counted and predicted as the molecule of the rate. A model of least squares support vector machine optimized with particle swarm optimization was built to predict the settlement cost which could be used to draw the base data as the denominator of the rate. Thus, a dynamic calculation method of the subway project safety-civilized measure cost rate was worked out. Typical subway projects in Wuhan area were taken as examples to be analyzed. The results show that the rate calculated by the dynamic calculation method can reflect the demands of the subway projects for safe and civilized construction.

Key words: subway project, safety-civilized measure cost rate, settlement cost, dynamic calculation, particle swarm optimization-least squares-support vector machine(PSO-LS-SVM) model